Architectural Record
search
cart
facebook twitter linkedin youtube
  • Sign In
  • Subscribe
  • Sign Out
  • My Account
Architectural Record
  • NEWS
    • Latest News
    • Awards
    • Interviews
    • Obituaries
    • Podcasts
      • Design:Ed Podcast
      • Sponsored Podcasts
  • OPINION
    • Book Reviews / Excerpts
    • Exhibition Reviews
    • Forum
  • EXCLUSIVES
    • Videos
    • Design Vanguard
    • Top 300 Firms
    • Sponsored Content
    • Sponsored eBooks
    • From the Archives
  • CONTINUING ED
    • Editorial Continuing Ed
    • CE Center
    • CE Academies
  • PROJECTS
    • Buildings By Type
    • Reuse & Renovation
    • Museums & Arts Centers
    • Colleges & Universities
    • Multifamily Housing
    • Interiors
    • Lighting
    • Kitchen & Bath
  • HOUSES
    • Record Houses
    • House of the Month
    • Featured Houses
  • PRODUCTS
    • Products by Category
    • Record Products of the Year
    • Latest Products
  • EVENTS
    • Dates & Events
    • Record on the Road
    • Innovation Conference
    • Sustainability in Practice
    • Women In Architecture
    • Webinars
    • Ad Excellence Awards
    • Submit an Event
  • CONNECT
    • Ask RECORD AI
    • Newsletters
    • Contact
    • Advertise
    • Editorial Calendar
    • Store
    • Customer Service
  • SUBMIT
    • Submission Guidelines
    • RECORD Competitions
  • MAGAZINE
    • Subscribe
    • My Account
    • Digital Edition
    • Current Issue
    • Firm Pass
    • Historic Archive
Architecture News

At Ground Zero, Little Progress After Seven Years

By Sam Lubell
At Ground Zero, Little Progress After Seven Years

At Ground Zero, Little Progress After Seven Years

On the seventh anniversary of 9/11, there is nothing majestic about the 16-acre World Trade Center site, a construction zone informally called The Pit.

Photo © Joe Woolhead/courtesy Port Authority of New York and New Jersey

At Ground Zero, Little Progress After Seven Years

At Ground Zero, Little Progress After Seven Years

The 52-story, SOM-designed 7 World Trade Center (middle of photo) opened in 2006.

Photo © Joe Woolhead/courtesy Port Authority of New York and New Jersey

At Ground Zero, Little Progress After Seven Years

At Ground Zero, Little Progress After Seven Years

Site plan for Ground Zero.

Image courtesy Silverstein Properties

At Ground Zero, Little Progress After Seven Years

At Ground Zero, Little Progress After Seven Years

Rendering of Lower Manhattan’s future skyline.

Image courtesy dbox

At Ground Zero, Little Progress After Seven Years

At Ground Zero, Little Progress After Seven Years

Rendering of Freedom Tower by SOM.

Image courtesy Silverstein Properties

Gehry Designs First Big Project for Toronto

Gehry Designs First Big Project for Toronto

Rendering of Tower 2 by Foster + Partners.

Image courtesy Silverstein Properties

Gehry Designs First Big Project for Toronto

Gehry Designs First Big Project for Toronto

Rendering of Tower 3 by Rogers Stirk Harbour + Partners.

Image © Rogers Stirk Harbour + Partners/courtesy Silverstein Properties

At Ground Zero, Little Progress After Seven Years

At Ground Zero, Little Progress After Seven Years

Rendering of Tower 4 by Maki and Associates.

Image © Maki and Associates/courtesy Silverstein Properties

At Ground Zero, Little Progress After Seven Years

At Ground Zero, Little Progress After Seven Years

Rendering of WTC Transit Hub.

Image courtesy Silverstein Properties

Gehry Designs First Big Project for Toronto

Gehry Designs First Big Project for Toronto

National September 11 Memorial and Museum.

Image courtesy National September 11 Memorial and Museum

At Ground Zero, Little Progress After Seven Years

At Ground Zero, Little Progress After Seven Years

National September 11 Memorial and Museum.

Image courtesy National September 11 Memorial and Museum

At Ground Zero, Little Progress After Seven Years
At Ground Zero, Little Progress After Seven Years
At Ground Zero, Little Progress After Seven Years
At Ground Zero, Little Progress After Seven Years
At Ground Zero, Little Progress After Seven Years
Gehry Designs First Big Project for Toronto
Gehry Designs First Big Project for Toronto
At Ground Zero, Little Progress After Seven Years
At Ground Zero, Little Progress After Seven Years
Gehry Designs First Big Project for Toronto
At Ground Zero, Little Progress After Seven Years
September 10, 2008
After New York City’s Twin Towers fell in September 2001, rebuilding quickly—and majestically—seemed imperative. But seven years later, there is nothing majestic about the 16-acre World Trade Center site, a construction zone informally called The Pit.
 
In early July, the property owner, the Port Authority of New York and New Jersey, announced that all of the projects planned for Ground Zero were over budget and behind schedule. The authority’s executive director, Christopher Ward, delivered the bleak assessment during a meeting hosted by New York’s Downtown Alliance, a nonprofit that promotes development in Lower Manhattan. Ward noted straight off that most of the projects have been “driven by emotional and political needs,” and the costs and timetables initially presented to the public are unrealistic. “We are not going to make any of them,” he said.
 
While Ward was vague on details, a 34-page report the authority presented to New York Governor David Paterson pointed to 15 fundamental issues that are holding up progress. The report mentions rising construction costs, incessant demands of stakeholders, the lack of unified leadership, and the unprecedented scope of the redevelopment plan. Noting that there has been “no efficient decision-making process or steering committee,” Ward proposed that stakeholders come together and, by the end of September, set “clear and achievable timelines.”
 
Some found Ward’s announcement refreshingly honest. “It was clear he got it right away and understood what it was going to take to make this happen,” says T.J. Gottesdiener, FAIA, managing partner at Skidmore, Owings & Merrill (SOM). Others are not so hopeful. “People are fed up,” says Peter Slatin, editor of The Slatin Report, a popular commercial real estate Web site. The parties involved have cast aside the public interest, he says, and turned the rebuilding effort “into a circus for political and commercial interests.”
 
There are 26 projects totaling $15 billion planned for the site, according to The New York Times. The centerpiece of the scheme is the SOM-designed Freedom Tower, or 1 World Trade Center. Originally scheduled to be finished this year, construction of the 1,776-foot-tall skyscraper has inched along since foundation work began in 2006. Today, steel columns rise a mere 20 feet above street level.
 
Still, the Freedom Tower is faring better than Towers 2, 3, 4, and 5—designed by Norman Foster, Richard Rogers, Fumihiko Maki, and Kohn Pedersen Fox, respectively. Tower 2 is in the excavation stage, while foundation work on Towers 3 and 4 got under way in February. The Tower 5 project is at a standstill until the former Deutsche Bank building, at 130 Liberty Street, is demolished. Further dampening spirits is a weakening commercial real estate market in Manhattan. The only completed tower at Ground Zero — the 52-story, SOM-designed 7 World Trade Center, which opened in 2006—is only 75 percent filled.
 
Given the dire situation, project downsizing is likely. Santiago Calatrava’s transit hub, projected to cost up to $3.5 billion, already was scaled back: In July, the hydraulic system that would allow its roof to open and close was eliminated from the proposed design. A performing arts complex by Frank Gehry might not get built at all.
 
One landmark now under way is the National September 11 Memorial and Museum. The architect Michael Arad, with landscape architect Peter Walker, proposed the competition-winning scheme for the memorial: two pools in an 8-acre, tree-filled plaza. David Brody Bond Aedas designed the museum, located mostly below ground, with an entry pavilion by Snøhetta. Foundation work on both projects is nearing completion.
 
Joe Daniels, president of the memorial and museum, says it is essential that the memorial be open by the 10th anniversary of the terrorist attacks. The architect, while happy the project is moving forward, is not optimistic it will be finished by September 2011. “It’s a significant milestone,” Arad says, “and I’m disappointed that we’re not going to be able to meet it.”

Share This Story

Looking for a reprint of this article?
From high-res PDFs to custom plaques, order your copy today!

Post a comment to this article

Report Abusive Comment

Subscription Center
  • Create an Account
  • Start a Subscription
  • Manage My Account
  • Sign Up for Newsletters
  • Visit Customer Service
  • Update Preferences

More Videos

Sponsored Content

Sponsored Content is a special paid section where industry companies provide high quality, objective, non-commercial content around topics of interest to the Architectural Record audience. All Sponsored Content is supplied by the advertising company and any opinions expressed in this article are those of the author and not necessarily reflect the views of Architectural Record or its parent company, BNP Media. Interested in participating in our Sponsored Content section? Contact your local rep!

close
  • TAMLYN XtremeTrim Exterior Trim
    Sponsored byTamlyn

    Designing Cleaner Panel Facades: Why Exterior Trim Details Matter

  • Building with Vapor Barriers
    Sponsored byReef Industries, Inc.

    Vapor Barriers Help Control Moisture in Tighter Building Designs

  • Duct Interior with Prodeq System
    Sponsored byHenry, a Carlisle Company

    Designing Resilient Water Containment Systems

DESIGN:ED Podcast
Listen to Architectural Record’s DESIGN:ED Podcast

Events

June 10, 2026

Rethinking Stormwater – The Power of Porous Paving

Credits: 1 AIA LU/HSW; 1 AIBD P-CE; 0.1 ICC CEU

Learn how porous paving systems support stormwater management, reduce heat island effects, and enhance sustainable site design performance.

June 11, 2026

Very Early Warning Fire Detection for Mission-Critical Facilities

Credits: 1 AIA LU/HSW; 1 AIBD P-CE; 0.1 ICC CEU

Examine advanced fire detection strategies that support uptime and enhance safety in data centers and other mission-critical facilities.

View All Submit An Event

Products

2026 Architect's Square Foot Costbook

2026 Architect's Square Foot Costbook

See More Products

Popular Stories

Practice Matters illustration

What’s in a (Firm’s) Name? Thinking About Succession and Legacy

Coronado Bridge

The Architect’s Guide to San Diego

Practice Matters illustration

By the Numbers: Counting America's Architects

House on a Hill

Design Vanguard 2026: Forma

Crane Cove, ONO

Design Vanguard 2026 Winners

Broader Sustainability of CMU - Free Webinar - May 21, 2026

Related Articles

  • A Tale of Two Rebuilding Efforts at Ground Zero

    See More
  • St. Nicholas Greek Orthodox_result2.jpg

    Calatrava’s New St. Nicholas Church Opens at Ground Zero

    See More
  • Players on a World Stage

    Power at Ground Zero: Politics, Money, and the Rebuilding of Lower Manhattan

    See More

Related Products

See More Products
  • Web-Modern-chinese-architecture18-1920x1125.jpg

    Modern Chinese Architecture: 180 Years

  • bim design firms.jpg

    BIM for Design Firms: Data Rich Architecture at Small and Medium Scales

See More Products
×

The latest news and information

#1 Source for Architectural Design, News and Products

SUBSCRIBE
  • RESOURCES
    • Advertise
    • Contact Us
    • Submit
    • Store
  • ACCOUNT CENTER
    • Create an Account
    • Start a Subscription
    • Manage My Account
    • Sign Up for Newsletters
    • Visit Customer Service
    • Update Preferences
  • PRIVACY
    • PRIVACY POLICY
    • TERMS & CONDITIONS
    • DO NOT SELL MY PERSONAL INFORMATION
    • PRIVACY REQUEST
    • ACCESSIBILITY
  • SERVICES
    • Marketing Services
    • Reprints
    • Market Research
    • List Rental
    • Survey/Respondent Access
  • STAY CONNECTED
    • Linkedin
    • Facebook
    • Instagram
    • YouTube
    • X (Twitter)

Copyright ©2026. All Rights Reserved BNP Media, Inc. and BNP Media II, LLC.

Design, CMS, Hosting & Web Development :: ePublishing