The progressive aspect of the job—and a big departure for DOE—is that it was divided into three parallel design packages: site, shell and interiors. Similar to fast-tracking, the approach allowed the project to be done a couple of years faster than a design-bid-build approach.
But because DOE is not set up for fast-tracking, the DB team still had to respond to contract milestones at the end of schematic design, design development and construction documentation. However, the milestones did not coordinate with the way the team was packaging and delivering information. “We also needed to create document packages [for fieldwork] in the traditional way,” says Haselden.