Kansas City, Missouri

"Beer," Benjamin Franklin supposedly said, "is constant proof that God loves us and wants us to be happy." In fact, Franklin wrote those words about wine, not ale and lager. But a deep reverence for beer and the brewing process is evident in a finely tuned addition at the Boulevard Brewing Company in Kansas City, Missouri. Led by architects at El Dorado, which also acted as the general contractor, the brewery's Cellar 1 went from a utilitarian 1920s-era storage facility to a sleek, modern vitrine for vats of the increasingly popular Boulevard brand of brew. "When I started 15 years ago, we had 20 employees and made about 20,000 barrels of beer a year," says Mike Utz, a plant engineer at Boulevard. "This year we'll do about 175,000 barrels with 100 people. The company has grown like crazy." Today the company's beer is distributed in 25 states.

 

Boulevard hired El Dorado—which worked in close collaboration with a team of the client's own engineers—to add 28 feet of height to the existing 17-foot-tall "cellar."  The goal was to accommodate a production increase and provide access to new, much taller fermentation tanks, which employees access via hatchlike openings at the top of each one. The original masonry building housed tanks with a capacity less than half that of the new tanks, which, at 40 feet tall, hold up to 300 barrels of beer.

The expansion, a glass-and-steel top hat on the original early-20th-century building, also provides a comfortable work environment for the employees, explains Dali Grabar, Boulevard's engineering project manager. A corrugated, perforated-aluminum screen that hugs the structure's northwestern and southwestern facades passively maintains a temperate interior climate, preventing spikes in indoor temperature by reducing solar heat gain. "This summer we had temperatures up to 106 degrees, and I don't think we ever went above 82 degrees in the building," says Grabar. "Considering how much glass and daylight we have, I think it's amazing."

The addition's elegance gives no hint of a construction period full of technical and logistical acrobatics. "The brewery had to remain operational while we did this," says El Dorado principal Josh Shelton, describing a process that involved excavating earth to make way for a new 3-foot-deep mat-slab. While El Dorado retained Cellar 1's original floors and masonry walls, the team erected a steel moment frame inside the preexisting structure to support a steel-grate catwalk for access to the top of each tank. "And Boulevard was installing all this piping while the glaziers were out there installing glass," Shelton adds. "Because we were working in an old space, our project manager, Chris Burk, had to really figure out the quirks of the existing building: all the slopes of the floors, what was parallel, what wasn't. Chris was crawling around all the tanks and pipes before we even started."

On a recent visit, any sign of the former tangle has been replaced by a general sense of order. Two neat rows of four stainless-steel tanks run the length of the building, and the low hum of machines at work fills the air. The new cellar's high ceilings, columnlike tanks, and delicate light create a space that feels more like a Gothic cathedral than a factory. It's all fitting for America's favorite alcoholic beverage, Franklin-endorsed or not.

Completion Date: July 2012

Gross square footage: 2,000 square feet

Total construction cost: withheld

Owner: Boulevard Brewing Company

Architect:
El Dorado Inc.
510 Avenida Cesar E. Chavez
Kansas City, Missouri 64108
p. 816.474.3838
f. 816.474.0836

People

Owner: Boulevard Brewing Company

Architect: 
El Dorado Inc.
510 Avenida Cesar E. Chavez
Kansas City, Missouri 64108
p. 816.474.3838
f. 816.474.0836

Personnel in architect's firm who should receive special credit:
Josh Shelton, AIA
Principal in Charge

Associate architect(s)
Chris Burk (Project Manager/Job Supervisor)
Steve Salzer, AIA (Envelope Design)

Engineers:
Genesis Structures (Structural)
PKMR (MEP)

Consultant(s):
Lighting: Derek Porter Studio

Brewing Infrastructure, Design and Installation: Boulevard Brewing Company

General contractor: El Dorado Inc.

Photographer(s):
Mike Sinclair
816.842.1499

Renderer(s): Brandon Froelich

CAD system, project management, or other software used: Vectorworks

 

Products

Structural system
Moment steel frame with 25 ft structural cantilever.  Solid walls- Cold-formed steel stud framing, blown-in insulation, EPDM thermal barrier, aluminum furring channels, corrugated perforated aluminum panels.

Exterior cladding
Glass curtain wall: EFCO 5600 Structural Silcione Glazed Curtain Wall, 1” I.G.U. w/ Solarban Coating

Rainscreen: Centria Econolap Wall Panel, Ultrapon Painted Aluminum

Moisture barrier: Firestone EPDM

Roofing
Built-up roofing: Firestone SBS Modified Bitumen roofing membrane

Other: Firestone Ultraply Platinum TPO Roofing System

Glazing
Glass: SBS Glass Curtain Wall (see above)

Doors
Metal doors: Mesker, A6O Galvannealed

Hardware
Locksets: Von Duprin

Closers: LCN

Exit devices: Von Duprin

Interior finishes
Paints and stains: Sherwin Williams, Macropoxy 646 Past Cure Epoxy + Sher-cryl HPA High Performance Acrylic

Paneling: Firestone Kynar Painted Galvanized, Stainless Steel

Lighting
Task lighting & Interior ambient lighting: Copper Lighting-Metalux UT3 Vaportite

imming System or other lighting controls: Wattstopper Motion Sensor